Easy Chester with a Long Duration Unit extends a customer’s charging tests to observe behaviour beyond a short functional check.

System of the Month March 2025: Easy Chester with Long Duration Unit

The configuration

  • Easy Chester with Long Duration Unit
  • Published configuration: 1.8 kW
  • Charging tests up to 60 minutes

The engineering task

Some charging behaviours become visible only after a session has been running for a while. A brief start-and-stop test cannot show the same operating history.

The configuration

The featured Easy Chester setup uses a Long Duration Unit for charging tests of up to 60 minutes at the reported 1.8 kW operating point.

The test focus

The extended session helps the customer examine charging continuity and the station’s response over time. This setup tests the charging interface; it does not add OCPP backend analysis.